K
kfowler
I would like to generate a graph showing total actual work and remaining work
for a top level task over time (week), This would enable me to show the
projected remaining work through the duration of the project as it decreases
from N to 0, and show the actual work completed though the duration of the
project as it increases from 0 to N.
The canned visual reports don't allow me to do this (that I can see anyway).
Maybe I'm missing something. I also can't see how to customize a visual
report that will do what I want.
Using Microsoft Project 2007 (not the Server edition)
Thanks,
Kevin
for a top level task over time (week), This would enable me to show the
projected remaining work through the duration of the project as it decreases
from N to 0, and show the actual work completed though the duration of the
project as it increases from 0 to N.
The canned visual reports don't allow me to do this (that I can see anyway).
Maybe I'm missing something. I also can't see how to customize a visual
report that will do what I want.
Using Microsoft Project 2007 (not the Server edition)
Thanks,
Kevin