A
alex
Hi,
Knowledege of EPM 2007:
2 years.
Issue:
Remaining work impact duration.
Understand the capacity of the resource.
Context:
I create a project with one task during 5 days(monday to friday, 8 hours by
day) with 5 resources assigned.
The task is type fixed duration, each resource has 40 hours planified during
this week.
Each resource record hours between the begin and the end.
The planified hours haven't been totally consummed.
So there is remaining work on the task.
Specially one resource records:
9 - 2.5 - 8 - 4 - 2.5.
the system decides to put the remaining work to the next monday: 14 hours.
the duration change to 5.85 but my point of view is the duration should be 6
(monday to monday).
For continu, I see the % units of the resource, it's 206%.
I know the %units is associate to the most important value of planified work
or real work.
So in that case, the maximal is 14 hours in the work.
I try to understand, but what is the relation between 206% and 14hours?.
Picture about the project:
http://docs.google.com/View?docid=dgq4sw2r_20428bms5gfc
I appreciate a return, it's not the first time I see this weird behavior.
And for the project manager it's difficult to understand this point and take
the right decision.
thanks,
best regards,
Alexandre BARAULT
Knowledege of EPM 2007:
2 years.
Issue:
Remaining work impact duration.
Understand the capacity of the resource.
Context:
I create a project with one task during 5 days(monday to friday, 8 hours by
day) with 5 resources assigned.
The task is type fixed duration, each resource has 40 hours planified during
this week.
Each resource record hours between the begin and the end.
The planified hours haven't been totally consummed.
So there is remaining work on the task.
Specially one resource records:
9 - 2.5 - 8 - 4 - 2.5.
the system decides to put the remaining work to the next monday: 14 hours.
the duration change to 5.85 but my point of view is the duration should be 6
(monday to monday).
For continu, I see the % units of the resource, it's 206%.
I know the %units is associate to the most important value of planified work
or real work.
So in that case, the maximal is 14 hours in the work.
I try to understand, but what is the relation between 206% and 14hours?.
Picture about the project:
http://docs.google.com/View?docid=dgq4sw2r_20428bms5gfc
I appreciate a return, it's not the first time I see this weird behavior.
And for the project manager it's difficult to understand this point and take
the right decision.
thanks,
best regards,
Alexandre BARAULT