A
alex
Hi,
Context:
I change the work contour and there is an impact on my work.
Unexpected behavior:
I have a resource with 4 hours of capacity by day.
http://docs.google.com/Doc?id=dgq4sw2r_2082gtpw3ghh
I record 2 hours of actual work. So Microsoft Project allocates the
remaining work on the following days.
I change the work contour for another one, and i can see my work is changed.
My task is in fixed duration. I expected from Project to have a delivery
according to my configuration not a change of work.
So I should put the old value after to do that.
I choose fixed duration because I wish to keep my start and end date as I
define.
I don't see solution except to record hours manually, it's not an efficient
process.
My point of view is it's not possible to do what I expected and in that
case, this option shouldn't be used after the record of the first actual. I
can use it just when I create the project and establish the first baseline.
What is your point of view and feedback?
best regards,
Alexandre BARAULT
Context:
I change the work contour and there is an impact on my work.
Unexpected behavior:
I have a resource with 4 hours of capacity by day.
http://docs.google.com/Doc?id=dgq4sw2r_2082gtpw3ghh
I record 2 hours of actual work. So Microsoft Project allocates the
remaining work on the following days.
I change the work contour for another one, and i can see my work is changed.
My task is in fixed duration. I expected from Project to have a delivery
according to my configuration not a change of work.
So I should put the old value after to do that.
I choose fixed duration because I wish to keep my start and end date as I
define.
I don't see solution except to record hours manually, it's not an efficient
process.
My point of view is it's not possible to do what I expected and in that
case, this option shouldn't be used after the record of the first actual. I
can use it just when I create the project and establish the first baseline.
What is your point of view and feedback?
best regards,
Alexandre BARAULT