P
prashanth.sharangapani
Dear MPP users,
I need one help. I use MPP 2003.
1. Let us say, I have a task A that has a planned work of 40 hours,
spanning Monday through Friday. This task has a resource 'R'
allocated. 'R' is supposed to spend 8 hours every day.
2. Now, on the 'next' Monday, when I want to take status from 'R', I
find from his timesheet, that he has over stayed and completed the
task in 4 days.
3. I now go to the 'Actual Work' column, enter 40, and then go to the
'Actual Finish' and say that the task finished on Thursday as against
a planned finish of Friday.
4. At this point I would expect MPP to change the units on 'R' to
indicate that, in reality, 'R' was overloaded and spent effort
equivalent to 125% units (as against planned 100% units planned).
Issue: (4) above does not work. When I enter the actual finish as
Thursday, then the MPP will go and change the 'Actual Work' to what is
thinks is possible in 4 days. Since I want the actual work to be
accurate, I'm forced to live with a situation where the actual finish
is incorrect. How do I resolve this situation?
Thanks in advance.
Prashanth
Bangalore, India
I need one help. I use MPP 2003.
1. Let us say, I have a task A that has a planned work of 40 hours,
spanning Monday through Friday. This task has a resource 'R'
allocated. 'R' is supposed to spend 8 hours every day.
2. Now, on the 'next' Monday, when I want to take status from 'R', I
find from his timesheet, that he has over stayed and completed the
task in 4 days.
3. I now go to the 'Actual Work' column, enter 40, and then go to the
'Actual Finish' and say that the task finished on Thursday as against
a planned finish of Friday.
4. At this point I would expect MPP to change the units on 'R' to
indicate that, in reality, 'R' was overloaded and spent effort
equivalent to 125% units (as against planned 100% units planned).
Issue: (4) above does not work. When I enter the actual finish as
Thursday, then the MPP will go and change the 'Actual Work' to what is
thinks is possible in 4 days. Since I want the actual work to be
accurate, I'm forced to live with a situation where the actual finish
is incorrect. How do I resolve this situation?
Thanks in advance.
Prashanth
Bangalore, India