Hi Lynn,
I'm afraid you can't have a task scheduled against two time zones. I
would schedule the tasks by when the resources will be working on the
tasks.
I suggest setting the project calendar up as normal for the timezone
where the project manager is going to be working. Then create a
calendar (Tools > Change Working Time) with the offset for the other
time zone. Then apply that calendar either to the resources who will
be working or apply the calendar as a task calendar.
So, for example, you are in the Eastern US time zone (GMT-5). Create
the project calendar as usual and set the US resources up with that
calendar as their base. Then create the GMT calendar with the
appropriate off-set in time. If your working day is 08:00 - 17:00,
the working time in the GMT would be 03:00 - 12:00.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project