T
think0rdie
After installing project server 2007 SP2, timephased sheet of
"My Task" comes to be always displayed in 'days' not in 'hours'.
E.g. '0.125 days' or '0.75 days' instead of '1 hours' or '6 hours'.
When I edit the web parts, I can temporarily change into 'hours'.
However, after switching other views on PWA2007, then
coming back to "My Task" timephased sheet, it goes back to 'days'.
How can I permanently set the default unit to HOURS,
not DAYS of timephased sheet??
"My Task" comes to be always displayed in 'days' not in 'hours'.
E.g. '0.125 days' or '0.75 days' instead of '1 hours' or '6 hours'.
When I edit the web parts, I can temporarily change into 'hours'.
However, after switching other views on PWA2007, then
coming back to "My Task" timephased sheet, it goes back to 'days'.
How can I permanently set the default unit to HOURS,
not DAYS of timephased sheet??