How to display Timephased sheet of "My Task" PWA2007 in hours

T

think0rdie

After installing project server 2007 SP2, timephased sheet of
"My Task" comes to be always displayed in 'days' not in 'hours'.

E.g. '0.125 days' or '0.75 days' instead of '1 hours' or '6 hours'.

When I edit the web parts, I can temporarily change into 'hours'.

However, after switching other views on PWA2007, then
coming back to "My Task" timephased sheet, it goes back to 'days'.

How can I permanently set the default unit to HOURS,
not DAYS of timephased sheet??
 
B

Ben Howard

Hi,

Can you check that you are changing the web parts permenantly using Site
Actions, rather than "personalise my page".
 
T

think0rdie

Yes, I'm system administrator of PWA2007 and edit the shared web parts
configuration, NOT my personal web parts configuration.

regards,
 