M
Mike
Hi,
I've been reading some older posts to understand why I'm seeing an
overallocated resource in the Resource Graph but not in the hours of Work;
it's not quite clear to me yet...
My resource is set at Max Units of 50% and, over the course of a couple of
weeks, he has work scheduled for 4 hours or less each day (this makes sense
at 50% availability). However, the graph shows percentages on some of the
days far above 50%, e.g. one day shows 3.85 hours of Work as taking 88% of
the resource's availability.
Leveling is set to Hour-by-Hour and from what I've read so far, the resource
probably has some tasks overlapping by at least a minute since leveling by
Minute-by-Minute clears the overallocation. Am I on track here so far?
Should I leave leveling at Minute-by-Minute? Are there reasons I shouldn't
go to that much resolution?
These overallocations occur as I'm entering the Actual Work values each week
after which Project levels the tasks. Thanks.
I've been reading some older posts to understand why I'm seeing an
overallocated resource in the Resource Graph but not in the hours of Work;
it's not quite clear to me yet...
My resource is set at Max Units of 50% and, over the course of a couple of
weeks, he has work scheduled for 4 hours or less each day (this makes sense
at 50% availability). However, the graph shows percentages on some of the
days far above 50%, e.g. one day shows 3.85 hours of Work as taking 88% of
the resource's availability.
Leveling is set to Hour-by-Hour and from what I've read so far, the resource
probably has some tasks overlapping by at least a minute since leveling by
Minute-by-Minute clears the overallocation. Am I on track here so far?
Should I leave leveling at Minute-by-Minute? Are there reasons I shouldn't
go to that much resolution?
These overallocations occur as I'm entering the Actual Work values each week
after which Project levels the tasks. Thanks.