Project Tutorial Issue in Project 2003

M

Maurice

Presently progressing through the 'Create Scheduling Tool' excercise at URL:
http://www.microsoft.com/office/com...spx?lang=en&cr=US&dg=microsoft.public.project

The tasks of: Fixed Duration, Units, and Work have been entered under Tasks
in their respective 'cells'. Excercise says to: In the project schedule,
click in the Type field for the Fixed Duration task, click the arrow, and
then click Fixed Duration.

From the present view I cannot find a view that will allow me to complete
the above paragraph. Guidance sought
 
M

Maurice

Much thanks for your timely response. The lesson requires that I go to the
actual column named 'Type' created in the earlier part of the lesson which I
can only find in the 'resource usage' view. Clicking on the task itself does
not allow me to procede. Much thanks for your continued support.
 