Presently working the Microsoft Lesson of Scheduling at the website of:
http://office.microsoft.com/trainin...ID=RP010784011033&CTT=6&Origin=RC010779041033
Was able to set the tasks but the instructions make mention of the Increase
duration for the task that reads:
In your project schedule, click the Fixed Duration task.
In the Duration field, type 10d and press ENTER.
Note You may need to scroll right to see the Duration field.
Total hours of work for this task are now 80.
Where can I find the 'total hours' The duration of 10d is seen but not the
total hours. Is a change of view required? Guidance sought.
http://office.microsoft.com/trainin...ID=RP010784011033&CTT=6&Origin=RC010779041033
Was able to set the tasks but the instructions make mention of the Increase
duration for the task that reads:
In your project schedule, click the Fixed Duration task.
In the Duration field, type 10d and press ENTER.
Note You may need to scroll right to see the Duration field.
Total hours of work for this task are now 80.
Where can I find the 'total hours' The duration of 10d is seen but not the
total hours. Is a change of view required? Guidance sought.