C
CRat
I have an engineering drawing release schedule,. I have a resource
"Designer" and 14 available designers.
Project will assign 80 hours of work for a 10 day task. Depending on the
type of task it is (whether fixed duration or fixed work) - adjusting the
work value (hours) will either change the resource % assignments, or the
duration.
I am trying to get a better value of the work, while maintaining the task
duration and the % of time I'm using the resource.
In the 80 hours example above, I think it's really only going to take 40
hours of the designers work time in the 80 hours span time, but I don't want
to have him reassigned elsewhere. The other 40 hours in that span will be
filled with miscellaneous activities: meeting support, writing activity
reports, etc.
So, is there anyway to say a task will take 80 hours, but only worth 40 in
the bean counting world, with out reassigning the designer to another drawing?
"Designer" and 14 available designers.
Project will assign 80 hours of work for a 10 day task. Depending on the
type of task it is (whether fixed duration or fixed work) - adjusting the
work value (hours) will either change the resource % assignments, or the
duration.
I am trying to get a better value of the work, while maintaining the task
duration and the % of time I'm using the resource.
In the 80 hours example above, I think it's really only going to take 40
hours of the designers work time in the 80 hours span time, but I don't want
to have him reassigned elsewhere. The other 40 hours in that span will be
filled with miscellaneous activities: meeting support, writing activity
reports, etc.
So, is there anyway to say a task will take 80 hours, but only worth 40 in
the bean counting world, with out reassigning the designer to another drawing?