PWA Timesheet updation

S

Sneha Satish

Hi,

A resource is trying to update an activity assigned to him from PWA. On one
of the days, the resource has spent 10 hours on an activity but a resource
availability is only 8 hrs per day in the resource calendar. The timesheet
view of PWA does not allow the resource to update the time spent as 10 hours
on that particular day. Is there any solution to this?
 
M

Mike Glen

Hi Sneha ,

Again, please post on the server newsgroup. Please see FAQ Item: 24.
Project Newsgroups. FAQs, companion products and other useful Project
information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top