Is it possible when receiving updates via projectserver to view how much progress a resource has made on a particular task since they last updated it

e.g. John has a 20 hour task and he updates me at the end of a day's work (he works an eight our day) and he's reported the task 40% complete (indicating that he's done 8 hours on the task that day). At the end of the next day the task report shows the task to be 50% complete, meaning that in his eight hour day he only completed two hours of his scheduled work, but not ACTUALLY telling me this. In this simple example it's easy to track in ones head but in a real project it's impossible. Is there a field which can display "work since last update"? or somehting similar

Thanks in advanc