I have been working and reworking the schedule in MS Project 2003 all week. I
am teaching myself as I go. I am having problems with assigning resources to
tasks. I assigned all the resources to tasks and was over allocated so I
removed them and started over and over and over. I am working with one
resource at a time now to understand how this is happening. The one resource
is over allocated with 2 one minute tasks on one day. The calendar is sent
up for an 8 hour work day. I am not sure how to fix this.