L
LakeHills
Hopefully an easy question; I'm trying to allocate resources to tasks that
have limited time (30-50%) to devote to my project. I can't seem to find a
way to have project automatically schedule the start and end dates
considering the duration I enter and the resource I assign. I'm sure I used
to do this...
E.g. Tom is available 50% of each of his 8 hour days. I schedule a task for
1 day (8 hours) and assign Tom to start on Monday. I expect him to finish
Tuesday but project shows him finishing the same day (Monday).
Any Ideas?
have limited time (30-50%) to devote to my project. I can't seem to find a
way to have project automatically schedule the start and end dates
considering the duration I enter and the resource I assign. I'm sure I used
to do this...
E.g. Tom is available 50% of each of his 8 hour days. I schedule a task for
1 day (8 hours) and assign Tom to start on Monday. I expect him to finish
Tuesday but project shows him finishing the same day (Monday).
Any Ideas?