R
redmadcap
I am using MSP 2003. My schedule includes trades as resources (ex
welders, mechanics, etc). We are working on a two shift schedule tha
goes from 7:30-17:30 and 18:30-4:30. I have defined the work day as:
00:00 - 4:30
7:30 - 17:30
18:30 - 00
My concern is getting the correct resource usage. I have tw
problems:
1)I really want to get the resource usage per shift, but for a variet
of reasons I can't create a differentiation between the trade names (ex
welder-shift 1 and welder-shift 2). So if I ran a usage report, it wil
give total day usage of that trade (welder)
2) In addition, because the shift crosses over midnight, a resourc
usage report per day will give: second half last night's 2nd shift
today's day 1st shift + beginning half of 2nd shift. This might b
quite different from the full two shifts on a given day.
Question:
How can I obtain a resource usage report per shift, even if one of th
shifts crosses over midnight into the "next day"?
Thanks a ton
welders, mechanics, etc). We are working on a two shift schedule tha
goes from 7:30-17:30 and 18:30-4:30. I have defined the work day as:
00:00 - 4:30
7:30 - 17:30
18:30 - 00
My concern is getting the correct resource usage. I have tw
problems:
1)I really want to get the resource usage per shift, but for a variet
of reasons I can't create a differentiation between the trade names (ex
welder-shift 1 and welder-shift 2). So if I ran a usage report, it wil
give total day usage of that trade (welder)
2) In addition, because the shift crosses over midnight, a resourc
usage report per day will give: second half last night's 2nd shift
today's day 1st shift + beginning half of 2nd shift. This might b
quite different from the full two shifts on a given day.
Question:
How can I obtain a resource usage report per shift, even if one of th
shifts crosses over midnight into the "next day"?
Thanks a ton