F
Federico Bravo
Hi everybody. I am using Project 2007 (Standard). I have a fixed work,
40 hours task. I have 2 resources assigned at 100% units, both with a
standard calendar (40 hrs/week). The duration is 5 days as a
conseguence. Let's say that resource A is now available at only 50%.
Project assigns 4 hours to resource A on each of the 5 days, while
resource B is assigned 8,8,4 hours in the first trhee days of the
week.
It seems like that when changing %Units assignments, Project tries to
keep the duration unchanged. Is there a way to tell Project to try to
minimize duration when changing resource %Units assignments? In this
case the assignments could be:
A: 4,4,4,0
B:8,8,8,0
The duration would then be 4 days instead of 5.
Thank you in advance for your kind help.
Federico Bravo.
40 hours task. I have 2 resources assigned at 100% units, both with a
standard calendar (40 hrs/week). The duration is 5 days as a
conseguence. Let's say that resource A is now available at only 50%.
Project assigns 4 hours to resource A on each of the 5 days, while
resource B is assigned 8,8,4 hours in the first trhee days of the
week.
It seems like that when changing %Units assignments, Project tries to
keep the duration unchanged. Is there a way to tell Project to try to
minimize duration when changing resource %Units assignments? In this
case the assignments could be:
A: 4,4,4,0
B:8,8,8,0
The duration would then be 4 days instead of 5.
Thank you in advance for your kind help.
Federico Bravo.