J
jpclarkmba
I've a question about how to adjust actuals after setting a baseline.
Here is what I do:
1. Create a "Fixed Duration / Non-Effort Driven" task.
2. Set "Duration" to 5 days.
3. Set "Work" to 15 hours.
4. Assign a Resource. (They will show 38%)
5. Set my baseline.
Now I begin tracking actuals.
6. Enter 10 hours actually worked.
I then realize that the task is actually done, and my original estimate
was to high. I need to:
a) Set "Work" to 10 hours. (Obviously 5 lower than my baseline.)
b) Have my "Duration" REMAIN THE SAME.
- and thus -
c) Have the "Units" of the resource fall automatically.
How do I accomplish this? No matter what I try, the "Units" for the
resource remain unchanged - it keeps changing either my "Duration" or
"Work".
Here is what I do:
1. Create a "Fixed Duration / Non-Effort Driven" task.
2. Set "Duration" to 5 days.
3. Set "Work" to 15 hours.
4. Assign a Resource. (They will show 38%)
5. Set my baseline.
Now I begin tracking actuals.
6. Enter 10 hours actually worked.
I then realize that the task is actually done, and my original estimate
was to high. I need to:
a) Set "Work" to 10 hours. (Obviously 5 lower than my baseline.)
b) Have my "Duration" REMAIN THE SAME.
- and thus -
c) Have the "Units" of the resource fall automatically.
How do I accomplish this? No matter what I try, the "Units" for the
resource remain unchanged - it keeps changing either my "Duration" or
"Work".