M
Mike Betzler
We're in the planning process of setting up a project so many values are
subject to change per meetings, discussions, etc.
I've revised some of my resource max units, but my new value is not
reflected in the assigment units. I do revise the max units - in the
resource view. The project is quite large, but with few resources so
deleting and re-adding the resource really isn't a viable option. ?
For the sake of curiosity of revised max units to high and low values just
to see if this affects assignment units, i.e., 100%, 150%, 1%, etc., - no
change. What am I missing?
Any and all appreciated!
subject to change per meetings, discussions, etc.
I've revised some of my resource max units, but my new value is not
reflected in the assigment units. I do revise the max units - in the
resource view. The project is quite large, but with few resources so
deleting and re-adding the resource really isn't a viable option. ?
For the sake of curiosity of revised max units to high and low values just
to see if this affects assignment units, i.e., 100%, 150%, 1%, etc., - no
change. What am I missing?
Any and all appreciated!