S
seven_percent
I have a task, let's call it Development, which has three subtasks,
we'll call those Requirements, Coding, Debugging. The three subtasks
start on the same day, with no predecessors, and last the same amount
of time: 160 hours each. I would expect to see the total for
Development, then, as 160 hours. Instead, it is 168 hours. If I
change the duration of the three subtasks to 154, the duration for
Development becomes 162. Thus, the value for the parent task
Development is always 8 hours more than the subtasks. Anyone know what
causes this and how to fix it? I have similar scenarios in my project
but this is the only case where this is happening.
we'll call those Requirements, Coding, Debugging. The three subtasks
start on the same day, with no predecessors, and last the same amount
of time: 160 hours each. I would expect to see the total for
Development, then, as 160 hours. Instead, it is 168 hours. If I
change the duration of the three subtasks to 154, the duration for
Development becomes 162. Thus, the value for the parent task
Development is always 8 hours more than the subtasks. Anyone know what
causes this and how to fix it? I have similar scenarios in my project
but this is the only case where this is happening.