R
Ravi
Hello. I am having a strange problem with MS Project 2007 stand alone
version. I am doing the following
1. Open a project plan in a PC with Project 2007 Version 12.0.4518.1014 MSO
12.0.6320.5000. The plan opens fine. I add a new task in between other
existing taks and none of the other tasks schedule is impacted as expected as
I have not established any links between new and existing tasks
2. Now I do the same in a different PC which has Project 2007 Version
12.0.6423.1000 MSO 12.0.6525.1000. The plan opens fine. I add a new task in
between other exisitng tasks and suddenly the schedule is changed impacting
all the tasks. This happens even if the newly added tasks is not linked to
any task and even if the new task is a milestone. The same scheduling issues
appear even if I just add a resource without allocating that resource to any
task.
Is this any particular version or patch issue? or is it something I need to
change in default setting?
Any help is appreciated as I am not able to use this plan on my PC and is
impacting my planning activities.
Thanks
Ravi
version. I am doing the following
1. Open a project plan in a PC with Project 2007 Version 12.0.4518.1014 MSO
12.0.6320.5000. The plan opens fine. I add a new task in between other
existing taks and none of the other tasks schedule is impacted as expected as
I have not established any links between new and existing tasks
2. Now I do the same in a different PC which has Project 2007 Version
12.0.6423.1000 MSO 12.0.6525.1000. The plan opens fine. I add a new task in
between other exisitng tasks and suddenly the schedule is changed impacting
all the tasks. This happens even if the newly added tasks is not linked to
any task and even if the new task is a milestone. The same scheduling issues
appear even if I just add a resource without allocating that resource to any
task.
Is this any particular version or patch issue? or is it something I need to
change in default setting?
Any help is appreciated as I am not able to use this plan on my PC and is
impacting my planning activities.
Thanks
Ravi