NoviceUser
I have a client using Project Server 2003. After they baseline a shedule, if
they create a new task by using the copy and paste function, it also copies
the baseline data (Baseline Cost, Baseline Work etc). However, the summary
values and project level value for the baseline is not changed.
When a new task is added after a Baseline is set, I would think that the
baseline data for the new task should be blank as that task wasn't part of
the previous baseline.
Is this an expected result or a bug? Is there a setting somewhere that
allows me to stop the baseline copying into the new task when using the
copy/paste function?
If I simply insert a new task, no baseline data exists (as you'd expect).
Also, does 2007 behave the same way?
Any help with this would be appreciated.
Peter
they create a new task by using the copy and paste function, it also copies
the baseline data (Baseline Cost, Baseline Work etc). However, the summary
values and project level value for the baseline is not changed.
When a new task is added after a Baseline is set, I would think that the
baseline data for the new task should be blank as that task wasn't part of
the previous baseline.
Is this an expected result or a bug? Is there a setting somewhere that
allows me to stop the baseline copying into the new task when using the
copy/paste function?
If I simply insert a new task, no baseline data exists (as you'd expect).
Also, does 2007 behave the same way?
Any help with this would be appreciated.
Peter