sdesomer
I have a project where for a couple of weeks I want a few of my resources to
work 10 hour days (their choice). After that they are back to 8 hour days. I
changed their indvidual resource calendars to work from 8:00 - 6:00. Resource
Usage shows 10 hours but seems to only schedule 8 hours anyway. For
explanation purposes assume Units=100% and Max Units=100%.
I know it is simple, but I can't figure it out. Thanks for your help