10 hours a day scheduled for some for a short time

S

sdesomer

I have a project where for a couple of weeks I want a few of my resources to
work 10 hour days (their choice). After that they are back to 8 hour days. I
changed their indvidual resource calendars to work from 8:00 - 6:00. Resource
Usage shows 10 hours but seems to only schedule 8 hours anyway. For
explanation purposes assume Units=100% and Max Units=100%.

I know it is simple, but I can't figure it out. Thanks for your help
 
M

Mike Glen

Hi sdesomer,

Welcome to this Microsoft Project newsgroup :)

I suggest you change the Date format to include times of the day, via
Tools/Options/View tab, so that you can confirm that the changes are being
taken into account. Then via Format/Timescale.../Non-working time tab,
change the calendar to one of the resource calendars. This should show the
full 10 hours per day.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top