What is the trick to allocating a resource to just 10 minutes a day? For instance for the duration of a project I just want a PM to show they spend 10 minutes reviewing a project plan etc.
instance for the duration of a project I just want a PM to show they spendMark said:What is the trick to allocating a resource to just 10 minutes a day? For
I'm finding that the hours get increased as I spread for example a 5 hourMark said:Thanks Dale, What is the "default" or most commonly used constraint type?
though the hours "appear" to add up, and in the task sheet view no hours areMark said:Yes, its a matter of wrapping your mind around "duration" vs. "Work".
Any suggestions for resolving conflicting resources? I'm finding that even
Gary L. Chefetz (MVP) said:Mark:
See the following FAQ for your answer to this one.
http://www.mvps.org/project/faqs.htm#Overallocation Occurring In Less Than One Day
--
Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com
-
though the hours "appear" to add up, and in the task sheet view no hours are
red, the resouce name is still "red" and for the life of me I cannot fine
the over allocation.