Hello,

When tasks with 100% complete will disappear from "My task" view ?
I'm working with "Current task".

Thanks

P.
 
G

Gérard Ducouret

Hello Poni,

With the standard setting, they will disappear 10 days after their finish
date.

Gérard Ducouret
 
R

reza

Poni...

If you want directly dissapear from my task...
open your project in Project Pro...add colum publish.
task with 100% set value to No....

hope this help
 