Kay
When I am tracking, I mark a task as 100%. My experience
with previous versions of Project is that it
automatically records the Start Date into the Actual
Date.
Now, however, when I mark 100% Project records the
current date as the start date. I don't want to have to
change the current date every time.
Why is this happening, and more importantly, how do I fix
it?
Thanks for the help-
Kay