What is the best way to take a task that is 2000 hrs and
will take 3 years to complete. This is a task that
someone will occasionally work on part time.
The question I have is, do I specify the duration in
days...i.e. 780 days...and then when I assign the
resource, enter in the hours that they will work on that
task...i.e. 2000?? Will that spread the hours out over
the 3 year span.....