2003: Ability to See Populated Work Baseline in Time Sheet

M

Marsha E.

We were able to add the work baseline column to the time
sheet, but the field did not populate.

Is this a bug?

Any help would be appreciated.

Thanks...Marsha
 
J

Jack D.

Marsha said:
We were able to add the work baseline column to the time
sheet, but the field did not populate.

Is this a bug?

Any help would be appreciated.

Thanks...Marsha

Did your project have a baseline set? Was the project published and update
requests sent?

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP
email: J -at- eM Vee Pee S dot COM


+++++++++++++++++++
 
D

Dale Howard

Marsha --

You first need to add the Baseline Work field to the list of published
fields in your current project. To do so, click Tools - Customize -
Published Fields, add Baseline Work to the list of published fields, and
then click OK. Afterwards, you will need to publish the assignments in your
project by clicking Collaborate - Publish - New and Changed Assignments.
This will populate the field in each user's timesheet.
 