[2003] How to replace a resource

R

Robert X

Hello,

In Project Server 2003, a task and its assignement have been published. I
need to replace the current resource by another one.
I publish again. Then I need to display the View Resource Assignments in PWA
2003.
But there, the task is shown as "Deleted" for the previous resource and the
PWA page is cluttered up with all this useless information.
How can I replace properly a resource by another one ?
Thanks for your help!

Robert
 