2007: Actual Time on Non Working Days ?

W

Woody

Hello,
Project Server 2007:
Is it possible to prevent users from entering actual time on non working
days in their timesheet ?
Thanks for your help

Woody
 
D

Dale Howard [MVP]

Woody --

No, I do not believe this is possible. Why would you want to do this
anyway? If a resource works on a Saturday or Sunday, why wouldn't you want
them to enter the time as they actually worked it? Let us know.
 
W

Woody

Dale --

Just to avoid the risk of typos: in that company nobody works on Saturdy or
Sundy.

Woody
 
D

Dale Howard [MVP]

Woody --

The employees at that company are very lucky. No, I do not believe there is
any way to prevent a resource from entering Actual Work on a Saturday or
Sunday in their Timesheet. If they do, their resource manager can reject
the Timesheet and state the reason is that actual was entered erroneously on
a weekend day. After correcting the error, the resource can resubmit the
Timesheet. Hope this helps.
 
Top