2007 build team resource availability display

R

Rudolf

Hi,

Has anyone seen this behaviour and knows the proper solution:
when building a team for a project the Build Team window is opened. Show
resource availability is standard turned on and 'use project start and finish
date' is selected. Yet all resources show an availability of 0h. Once the
selection is changed to 'from date to date' than the availibilty column is
filled. And these figures change as expected, when the selection is turned
bank into 'use project start and finish date'. So it seems that the
availability isn't refreshed when the build team window is opened.

Thankx in advance for your input.
 
D

Dale Howard [MVP]

Rudolf --

This is a known and reported bug in Project Server 2007. Whether Microsoft
will fix this particular bug in SP1 has yet to be seen. Hope this helps.
 
R

Rudolf

Hi Dale,

thanks for your reply.
I wasn't aware the bug was already reported.

regards,
Rudolf
 
Top