M
Matt Piazza, PMP
Does 2007 allow a budget to disappear if not used? My client wants to
forecast a resource at 10% level of effort for a maintenance role for 3
months. I used each scenario of the scheduling algorithms (Fixed
dur/unit/work w/ & w/o effort driven) to allow unused work hours to disappear
if not used. So far, each scenario only saved the unused work hours and
pushed these unused hours ahead of the status date.
We need this type of effort management to combine with each resource's
budget when working both LOE and Project work.
I am open to workable ideas....
forecast a resource at 10% level of effort for a maintenance role for 3
months. I used each scenario of the scheduling algorithms (Fixed
dur/unit/work w/ & w/o effort driven) to allow unused work hours to disappear
if not used. So far, each scenario only saved the unused work hours and
pushed these unused hours ahead of the status date.
We need this type of effort management to combine with each resource's
budget when working both LOE and Project work.
I am open to workable ideas....