Hi,
An additional question regarding timesheets andremainingwork
We have marked the option "Time entry by Timesheet only. Users will sync to
update tasks" (under "Task Settings and Display" in Server Settings).
Using this option we have some difficulties finding a way for the project
members to reportRemainingWork(because theRemainingWorkfield on the
Assignment Details page is grayed out).
Any suggestions to solve the problem?
The only solution we have identified so far is to rewrite/extent the
timesheet webpart.
Morten
Sorry, do not have an answer, but would love someone to try and answer
this question....
If you want to ensure that actual time is driven from the timesheet
update, how do you allow a team member to report remaining work.
option 1 - fill out remaining work in timesheet from clicking onto
task name to show the assignment details - greyed out.
option 2 - fill out timesheet then import time into "my tasks"; insert
remaining work as a column in "my assignments" view - field read only.
There must be something i am missing...
Anyone got past this yet...
???