We are trying to schedule with a 24 hour calendar that has been selected in
Global through Organizer. When we save the project to server the calendar is
being overwritten to Standard. This occurs in both SP1 (our test
evironement) and non-SP1 (our production environment) environements with the
local calendar option checked. What are we missing?
 
G

Gary L. Chefetz [MVP]

Paul:

Although I believe the best practice would be for you to create an
Enterprise calendar for this purpose, but if you must use a local base
calendar, you also must allow this through Project Server admin. In PWA, go
to Admin > Configure Server and check the box to allow local base calendars.
 
P

Paul Douglas

Thanks!

Gary L. Chefetz said:
Paul:

Although I believe the best practice would be for you to create an
Enterprise calendar for this purpose, but if you must use a local base
calendar, you also must allow this through Project Server admin. In PWA, go
to Admin > Configure Server and check the box to allow local base calendars.
 