35h and 40h/week calendars

M

Muriel Fournier

Hello,
MS Project Pro 2002 (French version) works with a 35h/week calendar.
Obviously, PWA works with a 40h/week calendar.

So a 4 days tasks in Project appears as 3,5 days in PWA !
A 5 days task in Project appears as 4,38 days in PWA !

How can I correct this stupid behavior ?

Thanks for help,

Muriel
 
Top