6HS as standard working time

H

HM2007

I define a new project. In Tools, Options, Calendar, I declare:
default start time: 12:00
default end time: 18:00
Hours per day: 6,00
Hours per week: 30
Days per month: 22

No resources are input.
When I input my first task starting on 11-02-2008 and ending on 13-02-2008 I
get a 3,33 days of duration
Which other parameter should I change to obtain a rounded calculation?
 
G

Gérard Ducouret

HM2007,
You have to adapt your calendar to these new schedule:
Tools / Change Working time...

Hope this helps,

Gérard Ducouret
 
Top