7 working days a week

A

Alain R.

Hi,

what should i modify to make every day of the week as working day ?
till now i was only able to make 6 working days per week.

i'm working on a personal project and i would like to use MS project
just as a storing project which later i will use for next project
planning based on real time spent on this project.

thx.

A.
 
J

JulieS

Hello Alain R.,

If you are using Project 2003:
Tools > Change Working Time
Click and drag in the column headings to select S through S
On the enter the working times.

If you are using Project 2007:
Tools > Change Working Time
Click the Work Weeks tab
Click the Details button.
Click on "Sunday" press and hold the Ctrl key and click on Saturday.
(both days should be highlighted)
Click in the radio button for "Set day(s) to these specific working
times" and enter the working times. Ensure you press tab after entering
the last "To" time.
Click OK to close the details dialog.
Click OK to close the Change working time dialog.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
S

Steve House

Just modify the Standard calendar to make Saturday and Sunday regular
working days. Tools/ChangeWorkingTime
 
J

Jan De Messemaeker

Hi,

Which version?
In 2007, Tools, Change Working Time, Work Weeks, Detail, Select the
remaining day then Set days to specific Working times.
ENTER before hitting OK

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 