I have a question about the patch that Micrsoft will give out for the 8 hour
workday bug (knowledge base article 331973).
The article describes the symptoms as appearing in Project Web Access.
However, my question relates to Project Professional (2002) itself. In
testing, I have scheduled a task with a duration of 50 days. I have a
resource calendar attached to a resource with alternating Mondays off.
Project does schedule the task with the correct Mondays off, but it only
shows 8 hours of work scheduled even though I have everything defined as a 9
hour workday (when I mean everything, I mean the calendar tab on the options
menu, and the calendar itself). Does the patch that Microsoft provides
correct this error?
workday bug (knowledge base article 331973).
The article describes the symptoms as appearing in Project Web Access.
However, my question relates to Project Professional (2002) itself. In
testing, I have scheduled a task with a duration of 50 days. I have a
resource calendar attached to a resource with alternating Mondays off.
Project does schedule the task with the correct Mondays off, but it only
shows 8 hours of work scheduled even though I have everything defined as a 9
hour workday (when I mean everything, I mean the calendar tab on the options
menu, and the calendar itself). Does the patch that Microsoft provides
correct this error?