8 Hour Work day patch question

J

John

I have a question about the patch that Micrsoft will give out for the 8 hour
workday bug (knowledge base article 331973).

The article describes the symptoms as appearing in Project Web Access.
However, my question relates to Project Professional (2002) itself. In
testing, I have scheduled a task with a duration of 50 days. I have a
resource calendar attached to a resource with alternating Mondays off.
Project does schedule the task with the correct Mondays off, but it only
shows 8 hours of work scheduled even though I have everything defined as a 9
hour workday (when I mean everything, I mean the calendar tab on the options
menu, and the calendar itself). Does the patch that Microsoft provides
correct this error?
 
G

Gary L. Chefetz [MVP]

John:

Did you apply the working hours change to the Enterprise Global? If so, did
you set the server to not allow local base calendars?
 
J

John

I did apply the working hours change to the Enterprise Global. I did not
set the server to not allow local base calendars.

Does the patch correct Project Pro 2002, or just time in PWA?
 
J

John

I changed the local base calendar switch on the server, I also double
checked the enterprise global and the time was a little not quite accurate
on that one, so I corrected that too. It all now seems to work properly.

Thanks for your assistance.
John
 