A
Annia
Hi all,
Im having a problem here and I havent found an answer in
the newsgroup so far.
Some of the Tasks __not Summary Tasks__ are not getting
%100 updated. The resources update their tasks as %100
complete but in Project professional they don't get
updated, they show as %99 complete. I dont have anyone
assigned to Summary tasks and it happens even if the task
is by itself and not a part of a summary task/assignment.
Can anyone help please?
Thanks,
Annia
Im having a problem here and I havent found an answer in
the newsgroup so far.
Some of the Tasks __not Summary Tasks__ are not getting
%100 updated. The resources update their tasks as %100
complete but in Project professional they don't get
updated, they show as %99 complete. I dont have anyone
assigned to Summary tasks and it happens even if the task
is by itself and not a part of a summary task/assignment.
Can anyone help please?
Thanks,
Annia