Hi everybody..
In out compony we use MS Project 2003 with Project Server. One of our
projectmanager has published a project. It can be senn in web access. But
wenn we try to open it in MS Porject Professionel, we can not see the tasks
(in no view).
Be get such an error message: (sorry for the trasnlation)
"computations cannot be accomplished . Circle purchase in task 151 auxiliary
masks to page driving profile of “ProjectXXXâ€. The successors of this task
refer predecessors on the same task or its. In order to remove for the circle
purchase the responsible person linkage, you mark both causing procedures and
click afterwards on the Standardsymbollyste on the switching surface
“linkages of procedure removeâ€. "
As far as I unsderstand, the pm has made an error with connection of tasks.
But how will avid that problem, as long as I see nothing (no tasks) in any
View.
Thanks..
In out compony we use MS Project 2003 with Project Server. One of our
projectmanager has published a project. It can be senn in web access. But
wenn we try to open it in MS Porject Professionel, we can not see the tasks
(in no view).
Be get such an error message: (sorry for the trasnlation)
"computations cannot be accomplished . Circle purchase in task 151 auxiliary
masks to page driving profile of “ProjectXXXâ€. The successors of this task
refer predecessors on the same task or its. In order to remove for the circle
purchase the responsible person linkage, you mark both causing procedures and
click afterwards on the Standardsymbollyste on the switching surface
“linkages of procedure removeâ€. "
As far as I unsderstand, the pm has made an error with connection of tasks.
But how will avid that problem, as long as I see nothing (no tasks) in any
View.
Thanks..