Xiao
Hello,
Project Professional 2007 + SP2
I have some tasks with Fixed Cost. But for some of them we got some more
cost.
In the Task Usage view, on the Actual Cost row, I enter $1200 instead of
$1000 for a specific week. The cost of the task for that week jumps to
$2200.
How to enter discrepancies of Actual Cost on Fixed Cost tasks?
Thanks
Project Professional 2007 + SP2
I have some tasks with Fixed Cost. But for some of them we got some more
cost.
In the Task Usage view, on the Actual Cost row, I enter $1200 instead of
$1000 for a specific week. The cost of the task for that week jumps to
$2200.
How to enter discrepancies of Actual Cost on Fixed Cost tasks?
Thanks