How to change Actual Cost for a Fixed Cost task?

X

Xiao

Hello,

Project Professional 2007 + SP2
I have some tasks with Fixed Cost. But for some of them we got some more
cost.
In the Task Usage view, on the Actual Cost row, I enter $1200 instead of
$1000 for a specific week. The cost of the task for that week jumps to
$2200.
How to enter discrepancies of Actual Cost on Fixed Cost tasks?
Thanks
 
R

Rod Gill

When entering actual cost, do so in the spreadsheet side of the view, or
make sure you delete the original $1,000 if it happened in a different week.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Xiao said:
Hello,

Project Professional 2007 + SP2
I have some tasks with Fixed Cost. But for some of them we got some more
cost.
In the Task Usage view, on the Actual Cost row, I enter $1200 instead of
$1000 for a specific week. The cost of the task for that week jumps to
$2200.
How to enter discrepancies of Actual Cost on Fixed Cost tasks?
Thanks



__________ Information from ESET Smart Security, version of virus
signature database 5110 (20100512) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 5110 (20100512) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top