A task's start and finish dates unchange when I adjust the duratio

W

wahta

Hi,

Is there anybody know, how can I do to change a task's start and finish
dates automically when I adjust the duration?

Thank you.

Regards,
wahta
 
R

Rod Gill

That should always happen unless you have calculation set to manual. Try
pressing F9. If that re-calculates go to Tools, Options, Calculation and
reset to Automatic for calculation.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




wahta said:
Hi,

Is there anybody know, how can I do to change a task's start and finish
dates automically when I adjust the duration?

Thank you.

Regards,
wahta

__________ Information from ESET Smart Security, version of virus
signature database 4590 (20091109) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4590 (20091109) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
V

vanita

Hi Wahta

Dates of your tasks would change based upon the predecessor links and
duration.

By default in MSP time scheduling calculations are automatic, so if you
change the duration related dates should change automatically. If this is not
happening go to Tools > options > calculations and select 'Automatic' option
for 'Calculation mode'.

I hope it helps.
Vanita
 