A Way to "Refresh" User Task View in PWA

T

Tim

I have noticed that several of my PWA users' available projects are not in
the correct order (and for at least one user she can see the tasks that she
is assigned to, but cannot see the top level project name). Also I think
this user also sees a duplicate of the top level project name for one of our
projects.

Question is--is there a way to "refresh" the "View my tasks" view so that
the projects are in proper order, all top level project names appear, and no
top level project names are duplicated. Essentially, I want them to see what
I see (which is the correct display of projects and assignments).
 
F

Fred Jones

Hi Tim,

1. Have you looked at 'republish assignments' in Project?
2. I found some odd problems when a task set as an outline level in Project
had a person assigned to both it and a task underneath the outline level. It
actually set up a circular reference that created some bizarre behaviors.
 