Hi,

how are cost calculated in the timesheet cube?

Thanks for any advice
Adrian
 
D

Dale Howard [MVP]

Adrian --

Project Server 2007 multiples the Standard Rate for the resource times the
number of hours entered on the Standard line on the timesheet, and multiples
the Overtime Rate times the number of hours entered in the Actual Overtime
Work line on the timesheet. The system used the Standard Rate and Overtime
Rate listed for each resource in the Enterprise Resource Pool. Hope this
helps.
 