About % Physical Complete

D

DimonD

How can I show "% Physical Complete" field in PWA?
Here are the steps that I followed:
- Added this field to list of Published Fields for the particular project
- Opened PWA Administration to setup the Timesheet View, BUT
- THERE IS NO SUCH A FIELD TO ADD!!! The only % fields are "% complete" and
"% work complete"! But where is "% physical complete"?
 
D

DimonD

But why??? This field is very important for us! We need our PWA users to fill
it. Otherwise we will not know the current state of the project?!?!

PM (the one who works with Project Prof) doesnt have such information, we
need our PWA users to enter this value.

Do you know any solution for this problem?


"Dale Howard [MVP]" пишет:
 
D

Dale Howard [MVP]

DimonD --

Perhaps you could use an enterprise field to capture this data, and then the
PM could enter this data manually in the Microsoft Project plan. I'm not
sure why Microsoft did not include this field. Sorry.
 