Hello Shiva,
MS Project manages 3 levels of calendars:
- Project Calendar : selected in Project / Project Information. By default,
it is the "Standard" calendar but you can create and use your own calendar.
- Resource calendar : which is often the Project calendar with some
exceptions : holidays... but which can be completely different
- Task calendar : for example you want to say that this task can only be
done on a weekend
While tasks don't have any resource assigned, they obey the Project Calendar
When tasks have resources assigned, they obey the resource calendar,
excepted when they have a specific task calendar : this last one has a
higher priority
Gérard Ducouret
What does a project Calendar mean? When I already select a calendar for
the project, still the tasks show the calendar selected as None
Any thoughts on this would be greatly appreciated.
Thank you
Shiva Chaitanya.
__________ Information provenant d'ESET Smart Security, version de la base
des signatures de virus 4203 (20090701) __________
Le message a été vérifié par ESET Smart Security.
http://www.eset.com
__________ Information provenant d'ESET Smart Security, version de la base des signatures de virus 4203 (20090701) __________
Le message a été vérifié par ESET Smart Security.
http://www.eset.com