About Reports

I

Ijaz

Hi:

My Question is regarding reports. I need to create a
report that will return the list of those resources who
are overcommitted (over 45 hrs of assigned tasks in a
single week).Also from where i can define the
overtimetask information in my project plan?

Your earliest response would b highly appreciated.

-Ijaz
 
D

Dale Howard [MVP]

Ijaz --

Have you examined the default Overallocated Resources report? Click Tools -
Reports - Assignments - Overallocated Resources to view the report. Would
this satisfy you reporting requirements?

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 