About Resource Usage view

D

DimonD

Why are some (actual) hours marked with red color? Also there values are very
strange - they are broken numbers! But why? Nor PM nor user enter such
values, just integers.
 
D

Dale Howard [MVP]

DimonD --

Projects that are not currently open may show red Actual Work values. When
you open those projects, the red will usually go away. This is is
oversight, I believe, in how the Resource Usage view should show data for
projects that are not currently open. Hope this helps.
 
D

DimonD

What do you mean by "Projects that are not currently open"?!? How can I see
anything if I dont open the proejct in MS Project Prof?!?!

Also why are the red hours broken numbers??? Nor PM nor user enter such
values, just integers.





"Dale Howard [MVP]" пишет:
 
D

Dale Howard [MVP]

DimonD --

When you open a project in Microsoft Project Professional, the Resource
Usage view shows the following for each resource:

1. All tasks that the resource is assigned to in the current project
2. All tasks that the resource is assigned to in other projects,
represented by a single line for each other project

Take a look at the red numbers. Are they from other projects? If so,
please reference my original explanation. If not, please explain further
what you see. Let us know.
 
D

DimonD

No Dale, those red broken numbers are not from other project but from the
project that I`ve opened. Why this happen?

Another q-n is why some of the work hours numbers are broken? Nor PM nor
user enter such values, just integers.

For ex I`ve entered my vacation in Admin Project as 8hours*10 w.days = 80
hours. Now when I look at it it see 8.03h*5 w.days = 80.3h
BUT WHY?!?!? MS Project is living it`s own life! He does what he wants and
even don`t notify the user-PM!

"Dale Howard [MVP]" пишет:
 