We have our PWA users to set hours on tasks every day.
The q-n is: how can we limit the number hours a day per tasks?
I know how to limit hours per task (there is a special setting), but what if
a resource is working on several tasks during a day? How to limit the hours`
summary?
 
D

Dale Howard [MVP]

DimonD --

You can't. Project Server allows you to set the maximum number of hours per
task but not per day. Hope this helps.
 
D

DimonD

But in this case one can enter 8 (or more) hours for each task per day and in
summary "one can report work" much more than a working day (8 hours by
default)!

How to overcome this?