I know that Project only supports percent complete and physical percent
complete when it comes to EV calculations. But I am curious if it's possible
to implement the 25/75 rule by using physical percent complete. Thus marking
any started tasks with 25% and any finnished tasks with 100%. Does anyone
know if this is possible? We are currently inn the prosess of moving over on
project server, is it possible to use the same practice on Project Server?