D
Daniel
Hello,
Usually Units = Work / Duration, but in some case it seems this formula
doesn’t work.
I performed some basic tests in project:
First test: I created a fixed duration task:
1 resource, Units = 100%, Work =5d, actual Work=0, so Duration = 5d and
Remaining work =5d
I changed Rem Work from 5d to 6d, the task become
Units= 120%, Work =6d, so Duration = 5d and Remaining work =6d which is fine.
Second test: I created a fixed duration task:
1 resource, Units = 100%, Work =5d, actual Work=1d, so Duration = 5d and
Remaining work=4d
I changed Rem Work from 4d to 5d, the task become
Units= 125%, Work =6d, so Duration = 5d and Act W.=1d, Remaining work =5d
Can anybody tell me why Unit=125%? (in both tests W/D=6/5=120%)
Usually Units = Work / Duration, but in some case it seems this formula
doesn’t work.
I performed some basic tests in project:
First test: I created a fixed duration task:
1 resource, Units = 100%, Work =5d, actual Work=0, so Duration = 5d and
Remaining work =5d
I changed Rem Work from 5d to 6d, the task become
Units= 120%, Work =6d, so Duration = 5d and Remaining work =6d which is fine.
Second test: I created a fixed duration task:
1 resource, Units = 100%, Work =5d, actual Work=1d, so Duration = 5d and
Remaining work=4d
I changed Rem Work from 4d to 5d, the task become
Units= 125%, Work =6d, so Duration = 5d and Act W.=1d, Remaining work =5d
Can anybody tell me why Unit=125%? (in both tests W/D=6/5=120%)